Maintenance Projects for summer 2017

Tannehill School is accepting bids on an extensive maintenance project for summer 2017. Photos below indicate some of the problems to be addressed.Bidder should be aware of time constraints involved with completion of project prior to start of classes in August. On site inspections can be arranged by calling Chris at 918-421-9226. Please send sealed bids to “Project Bid" Attention: John Wilcox, Tannehill School, 9283 Tannehill Rd., McAlester, OK 74501. Bids will be publicly opened in the office of the superintendent on Monday, June 12 at 12 noon.

Details of repairs include:

HVAC closet in library has a leak to repair and also  needs to be cleaned of mold and needs sheet rock replaced and painted with anti-fungal.

Two restrooms in portable (double-wide) classrooms have issues with floors around stools. Will need to have floors replaced and toilets reset.

Double wide portable classroom building also has roof leak that needs repair.

Gym: West side of gym roof needs to be replaced. Guttering needs to be replaced. Birds have infested the space through the exterior gap leading to extensive damage and staining of ceiling – needs to be cleaned.Also need drain guttering repairs; interior paint of all walls floor to ceiling (will require a lift or scaffold)  and coverage of black paint; repair of cracked finish materials behind goal. Repair of leaks at junction point (flashing) of main building and gym.

Photos of gym issues: